Skip to content

Chesterfield County, Virginia Updated 2026-11-20 05:40 EST

LIVE
Midlothian · Chester · Bon Air · Matoaca · Moseley · Ettrick · Enon Chesterfield Courthouse · Bermuda · Clover Hill · Dale · Midlothian Growth · Schools · Public safety · Government · Community

Jury Trial Set in County Widening Project Dispute

Richmond BizSensePublished

TL;DR

Chesterfield County faces a jury trial set for September 2027 in a dispute with contractor Branscome Operating LLC over $2.5 million in additional costs for the Iron Bridge Road widening project, one of three lawsuits totaling nearly $20 million against the county.

Image via Richmond BizSense

Quick facts

Who
Branscome Operating LLC and Chesterfield County
What
Jury trial scheduled in contractor dispute over Iron Bridge Road widening project; contractor seeking $2.5 million in additional costs; one of three related lawsuits with combined claims of nearly $20 million
When
Trial set for September 2027; Iron Bridge project completed in 2023
Where
Iron Bridge Road between Whitepine Road and Frith Lane, Chesterfield County, Virginia

The story

Chesterfield County is headed to trial in a dispute with contractor Branscome Operating LLC over additional payments for the recently completed Iron Bridge Road widening project. A jury trial has been scheduled for September 2027 and is expected to last eight days.

Branscome is seeking $2.5 million it claims the county owes for widening Iron Bridge Road from four to six lanes between Whitepine Road (near the county airport) and Frith Lane (near county government offices). The original contract was worth $11.6 million when awarded in 2021, and the project was completed in 2023.

The contractor argues that site conditions differed significantly from what was shown in the contract documents. Branscome claims the project was hampered by incorrect elevations in the plans, utility conflicts not identified in advance, and design changes that required work outside the original contract scope. According to Branscome, these issues resulted in cost overruns and project delays that entitled the contractor to additional compensation. The county has refused to pay the additional amount.

This Iron Bridge dispute is the first of three lawsuits Branscome has filed against Chesterfield County in less than a year. In August 2025, Branscome filed a second lawsuit seeking $3.4 million for a widening project on Winterpock Road. A third lawsuit arrived in November 2025, with Branscome claiming the county owes $13.7 million for a widening project on West Hundred Road in Chester. The claims across all three cases total nearly $20 million.

The West Hundred Road project illustrates a pattern Branscome claims plagued multiple contracts. That project involved widening a two-mile stretch of West Hundred to eight lanes between Bermuda Triangle Road and Rivers Bend Boulevard, plus improvements to adjacent roads. The contract began in October 2019 with an initial completion date of April 2022, but work continued until 2024. Although Chesterfield has already paid Branscome $40.6 million for that project, the contractor asserts defective plans, unanticipated subsurface conditions, unexpected utility impacts, and what it characterizes as the county's improper contract administration and poor communication contributed to the delays and cost increases justifying the additional claim.

Key players

  • Branscome Operating LLCContractor claiming county owes millions for road widening work
  • Chesterfield CountyCounty government defending against contractor's claims

Why it matters

The outcome of the Iron Bridge trial could affect whether Chesterfield faces substantial additional payments to Branscome and may influence how the county's other two disputed contracts with the contractor are resolved, potentially costing taxpayers millions depending on the verdict. The case also raises questions about the county's planning and contract oversight for major infrastructure projects.

Development timeline

  1. West Hundred Road project contract signed

    Branscome contracted to widen West Hundred Road and adjacent roads; initial completion target April 2022

    Source: West Hundred Road project contract signed
  2. Iron Bridge Road widening contract awarded

    $11.6 million contract awarded to Branscome for widening between Whitepine Road and Frith Lane

    Source: Iron Bridge Road widening contract awarded
  3. Iron Bridge Road project completed

    Four-to-six lane widening completed; Branscome subsequently seeks additional $2.5 million in costs

    Source: Iron Bridge Road project completed
  4. Second lawsuit filed

    Branscome filed second lawsuit seeking $3.4 million for Winterpock Road widening project

    Source: Second lawsuit filed
  5. Third lawsuit filed

    Branscome filed third lawsuit seeking $13.7 million for West Hundred Road widening project completed in 2024

    Source: Third lawsuit filed
  6. Trial date set for Iron Bridge dispute

    Eight-day jury trial scheduled for September 2027 in Iron Bridge Road contractor dispute

    Source: Trial date set for Iron Bridge dispute

Topics in this story

Chesterfield CountyBranscome Operating LLCIron Bridge Roadcontractor disputelawsuitroad wideninginfrastructurejury trial

Share

Reactions

Back to The Chesterfield Report

Growth & DevelopmentLocal Business

Chesterfield approves Nunnally Village project with Kroger, HCA hospital

Chesterfield County supervisors unanimously approved the 204-acre Nunnally Village mixed-use development featuring a 60-bed HCA hospital, Kroger supermarket, and up to 1,000 residential units on Hull Street in western Chesterfield.

Richmond BizSense