The Chesterfield Report heron emblem The Chesterfield Report

Hyperlocal news for Chesterfield County, Virginia.

LIVE
//Midlothian · Chester · Bon Air · Matoaca · Moseley · Ettrick · Enon //Chesterfield Courthouse · Bermuda · Clover Hill · Dale · Midlothian //Growth · Schools · Public safety · Government · Community //Midlothian · Chester · Bon Air · Matoaca · Moseley · Ettrick · Enon //Chesterfield Courthouse · Bermuda · Clover Hill · Dale · Midlothian //Growth · Schools · Public safety · Government · Community
Subscribe to free Chesterfield news →
Transportation Projects·

New Traffic Signal and Path Planned for Willis and Coach Roads

📍 Willis Road and Coach Road
View larger map ↗

TL;DR: Chesterfield County is planning a new traffic signal at the Willis Road and Coach Road intersection along with a shared-use path crossing the railroad to improve connectivity for drivers, cyclists, and pedestrians, with construction expected to begin in 2029.

Quick facts

  • Who: Chesterfield County
  • What: New traffic signal at Willis Road and Coach Road intersection, plus shared-use path crossing the railroad connecting existing facilities along Willis Road
  • When: Construction expected to begin in 2029
  • Where: Willis Road and Coach Road intersection

The story

Chesterfield County is moving forward with a transportation improvement project at the Willis Road and Coach Road intersection. The initiative includes construction of a new traffic signal at the intersection and a shared-use path that will cross the railroad to connect existing facilities along Willis Road, enhancing connectivity for drivers, cyclists, and pedestrians.

The project will be funded through a combination of federal and local money. Preliminary engineering activities are currently underway, with construction expected to begin in 2029. Traffic impacts during construction have not yet been determined.

Residents seeking more information about the project can contact JJ Banuelos at 804-748-1037 or BanuelosJ@chesterfield.gov.

Key players

  • Chesterfield County: Project sponsor and implementer
  • JJ Banuelos: County point of contact

Key dates

  • 2029: Construction expected to begin

Why it matters: The new traffic signal will improve safety and traffic flow at a key intersection, while the shared-use path will provide alternative transportation options for residents cycling or walking to and from areas along Willis Road.

Places

Development timeline

  1. 2026-08-18
    Preliminary engineering underway: County conducting preliminary engineering for Willis Road and Coach Road traffic signal and shared-use path project [source]
  2. 2029
    Construction anticipated to begin: Willis Road and Coach Road traffic signal and shared-use path construction expected to commence [source]

Related links

Read the original at Transportation Projects →

Sources

#Willis Road#Coach Road#traffic signal#shared-use path#pedestrian#cycling#railroad crossing#Chesterfield County
Reactions
← Back to The Chesterfield Report