Ettrick Train Station Gets $18.5M Upgrade After Closure Threat

Chesterfield on PointPublished

TL;DR

Officials broke ground on November 13 on an $18.5 million renovation of Ettrick Train Station in South Chesterfield, reversing a 2018 closure plan.

Image via Chesterfield on Point

Quick facts

Who
Virginia Passenger Rail Authority, Federal Railroad Administration, Amtrak, CSX, Chesterfield County leaders, U.S. Sen. Tim Kaine
What
Ceremonial groundbreaking for $18.5 million Ettrick Train Station renovation including new platform, ADA accessibility upgrades, and station improvements
When
November 13, 2026 (groundbreaking); construction begins spring 2027, estimated one-year completion
Where
Ettrick Train Station, South Chesterfield (off River Road near Virginia State University)

The story

Officials broke ground on November 13 on an $18.5 million renovation of Ettrick Train Station in South Chesterfield, marking the reversal of a contentious federal closure plan that had threatened the facility since 2018.

The ceremony brought together representatives from the Virginia Passenger Rail Authority, Federal Railroad Administration, Amtrak, and CSX, along with Chesterfield County leaders and U.S. Sen. Tim Kaine. The groundbreaking comes after years of advocacy by community members who fought to preserve the station at its original location near Virginia State University.

The renovation project will substantially upgrade the 71-year-old facility with a new 950-foot platform elevated 8 inches above the rail with a wheelchair lift enclosure, a full-length platform canopy, ADA-compliant ticket window and restrooms, updated interior and exterior signage, and sidewalk and ramp improvements. Construction is scheduled to begin in spring 2027 and take approximately one year to complete.

The station serves more than 60,000 riders annually, up 10 percent from 2025, with six roundtrip Amtrak trains daily. Its proximity to Virginia State University campus, located within half a mile, makes it a critical transportation hub for students without vehicles.

The project represents a dramatic turnaround for Ettrick Station. In May 2018, the Federal Railroad Administration announced plans to close the station and relocate service to Colonial Heights, citing infrastructure concerns. A volunteer group called Concerned Citizens of Ettrick mobilized opposition over the following years, arguing that relocation would disenfranchise VSU students and disrupt the community that had relied on the station since its 1955 opening. The group secured backing from U.S. Rep. Donald McEachin, state legislators, VSU's Board of Visitors, and the Chesterfield Board of Supervisors. By 2019, the Federal Railroad Administration indefinitely suspended the environmental assessment that had recommended closure, and the focus shifted to renovating the existing facility.

The Virginia Passenger Rail Authority acquired the property from CSX in 2021 as part of Virginia's broader rail transformation initiative. The $18.5 million renovation represents a significant state and federal investment in the station and aligns with other Ettrick village improvements including fire station modernization, library expansion, and affordable housing development.

Key players

  • Virginia Passenger Rail AuthorityProject lead agency overseeing the $18.5 million renovation
  • U.S. Sen. Tim KaineFederal official who attended groundbreaking and helped secure federal funding
  • Federal Railroad AdministrationFederal agency that abandoned 2018 closure plan and now supports renovation
  • Concerned Citizens of EttrickVolunteer advocacy group that successfully fought the 2018 closure threat
  • Virginia State UniversityAdjacent institution with significant ridership stakes

The case for

The renovation preserves essential passenger rail service to a transit-dependent population (VSU students) and maintains a community asset that has served the region for over 70 years, while investing in ADA compliance and modern infrastructure that will improve service quality and ridership.

The case against

The $18.5 million investment in a single rural station serving 60,000 annual riders could be evaluated as a significant expenditure per passenger compared to other regional transportation priorities, though federal and state funding mechanisms and the station's role as a critical connection point for university students and passengers between Petersburg and regional destinations offset cost-effectiveness concerns.

Why it matters

The renovation preserves critical rail access for Virginia State University students and local residents, delivering promised infrastructure improvements while reversing a threatened closure that would have disrupted transportation for a transit-dependent population. The project also signals state and federal commitment to rural rail infrastructure as part of Virginia's transportation modernization strategy.

Development timeline

  1. Federal Railroad Administration announces closure and relocation plan

    FRA identifies property in Colonial Heights as preferred location, recommending Ettrick Station closure

    Source: Federal Railroad Administration announces closure and relocation plan
  2. Concerned Citizens of Ettrick mobilizes opposition

    Volunteer group, led by community advocates, begins three-year effort to fight closure plan with support from U.S. Rep. Donald McEachin and state legislators

    Source: Concerned Citizens of Ettrick mobilizes opposition
  3. Federal Railroad Administration suspends closure assessment

    FRA indefinitely halts environmental assessment recommending closure; focus shifts to station renovation

    Source: Federal Railroad Administration suspends closure assessment
  4. Virginia Passenger Rail Authority acquires property from CSX

    VPRA takes ownership of Ettrick Station as part of Virginia rail transformation initiative

    Source: Virginia Passenger Rail Authority acquires property from CSX
  5. Ceremonial groundbreaking held

    Officials from VPRA, FRA, Amtrak, CSX, Chesterfield County, and U.S. Sen. Tim Kaine break ground on $18.5 million renovation

    Source: Ceremonial groundbreaking held

Topics in this story

Ettrickpassenger railinfrastructureAmtrakVirginia Passenger Rail AuthorityVirginia State Universitytransportation

Share

Reactions

Back to The Chesterfield Report