VDOT, County Plan Dundas Road Bridge Replacement

Transportation ProjectsPublished

TL;DR

Chesterfield County and VDOT have completed a $12.8 million replacement of the aging Dundas Road bridge over G Road, adding pedestrian accommodations between Meadowdale Boulevard and Strathmore Road.

Quick facts

Who
Virginia Department of Transportation and Chesterfield County
What
Dundas Road bridge replacement and pedestrian accommodation improvements
When
Completed April 2026
Where
Dundas Road (Route 641) from Meadowdale Boulevard to Strathmore Road, Chesterfield County

The story

Chesterfield County and the Virginia Department of Transportation have completed a $12.8 million bridge replacement project on Dundas Road (Route 641) over G Road. The new structure replaces a bridge built in 1961 and includes pedestrian accommodations, with work spanning from Meadowdale Boulevard to Strathmore Road.

Construction finished in April 2026 after beginning in spring 2024. During the project, westbound Dundas Road was reduced to one lane and eastbound traffic was detoured to Chippenham Parkway at Meadowdale Boulevard. The project aimed to improve infrastructure and pedestrian connectivity in the area.

According to 2017 traffic counts, Dundas Road carries approximately 7,100 vehicles per day. For more information, VDOT project manager Scott Chapman can be reached at 804-609-5277 or scott.chapman@vdot.virginia.gov.

Key players

  • Virginia Department of TransportationProject administrator
  • Chesterfield CountyProject partner
  • Scott ChapmanVDOT project manager

Why it matters

The completed project improves safety and accessibility for the 7,100 daily users of Dundas Road while replacing aging infrastructure that was over 60 years old. The addition of pedestrian accommodations enhances connectivity across the area.

Development timeline

  1. Spring 2024

    Dundas Road bridge replacement project begins

    VDOT and Chesterfield County initiate construction to replace the 1961-built bridge and add pedestrian accommodations

    Source: Dundas Road bridge replacement project begins
  2. Bridge replacement construction completed

    Dundas Road bridge replacement project finishes on schedule, replacing aging structure with new bridge and pedestrian facilities

    Source: Bridge replacement construction completed

Topics in this story

Share

Reactions

Back to The Chesterfield Report

Growth & DevelopmentSchools

Board Defers Data Center Taxes and Midlo School Site

Chesterfield's Board of Supervisors deferred decisions on data center tax allocation and a potential Midlothian Middle school site for the third time on November 18, with no timeline given for resolution.

The Richmonder